This week’s updates from the Wisconsin Department of Transportation (WisDOT) on road construction projects for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.
Barron County
Highway: US 53
- Location: 26th Avenue north of Rice Lake to Pine Grove Road south of Sarona
- Schedule: Sept. 5, 2023, to November 2024
- Cost: $21.89 million
- Description: Removing the existing and base course, placing a new base aggregate layer for drainage, replacing the pavement, rebuilding intersection approaches and installing cable barrier in the median between 26th and 27th avenues and a high-friction surface treatment on the pavement in the same area to reduce crossover and run-off-the-road crashes.
- Traffic impacts: Traffic on US 53 is limited to a single lane in each direction. The speed limit is reduced to 55 mph in the work zone.
Burnett County
- No current projects
Polk County
- No current projects
Rusk County
- No current projects
Sawyer County
Highway: County C
- Location: Couderay River Bridge west of the village of Couderay
- Schedule: Aug. 12 to November
- Cost: $874,296
- Description: Removing and replacing the bridge deck.
- Traffic impacts: County C is closed at the bridge.
Washburn County
Highway: US 53
- Location: Wildcat Road southeast of Spooner to County A
- Schedule: July 31, 2023, to November 2024
- Cost: $22.74 million
- Description: Removing the existing pavement and a portion of the existing base course; placing a new base aggregate layer for drainage and new concrete pavement; replacing pavement on the interchange ramps at US 63 and WIS 70; replacing the pavement on WIS 70 between the ramp terminals; rebuilding existing intersection approaches; and rehabilitating the bridges on US 53 over the Yellow River and US 63 and WIS 70 bridge over US 53.
- Traffic impacts: North- and southbound US 53 are open to a single lane in each direction, but the highway is anticipated to fully reopen by the end of the day Friday, Nov. 1.
Highway: US 53
- Location: 26th Avenue north of Rice Lake to Pine Grove Road south of Sarona
- Schedule: Sept. 5, 2023, to November 2024
- Cost: $21.89 million
- Description: Removing the existing and base course, placing a new base aggregate layer for drainage, replacing the pavement, rebuilding intersection approaches and installing cable barrier in the median between 26th and 27th avenues and a high-friction surface treatment on the pavement in the same area to reduce crossover and run-off-the-road crashes.
- Traffic impacts: Traffic on US 53 is limited to a single lane in each direction. The speed limit is reduced to 55 mph in the work zone.
Last Update: Nov 01, 2024 8:09 am CDT