This week’s updates from the Wisconsin Department of Transportation (WisDOT) on road construction projects for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.
Barron County
Highway: County P
- Location: County A North to 7th Avenue between Prairie Farm and Almena
- Schedule: June 12 to September
- Cost: $2.54 million
- Description: Pulverizing and relaying the existing pavement, placing asphalt pavement, completing culvert work and placing pavement markings.
- Traffic impacts: County P is closed to through traffic.
Highway: County SS
- Location: Chetek River Bridge in Chetek
- Schedule: May 3 to July
- Cost: $956,783
- Description: Replacing the bridge deck and girders, repairing and patching the abutments and making minor approach improvements.
- Traffic impacts: County SS is closed at the bridge, with traffic being detoured via County M, US 53 and County I.
Burnett County
Highway: WIS 70
- Location: St. Croix River Bridge west of Grantsburg
- Schedule: June 21 to October
- Cost: $1.25 million
- Description: Overlaying the bridge deck with concrete, making concrete structure repairs, repairing bridge joints, placing a polymer overlay on the sidewalk and replacing missing riprap, guardrail and approach pavement.
- Traffic impacts: The bridge is reduced to a single lane of traffic controlled by temporary signals.
Polk County
Highway: US 63
- Location: St. Croix/Polk County line to County J south of the village of Clayton
- Schedule: April 12 to late September
- Cost: $5.71 million
- Description: Replacing the pedestrian underpass east of 7th Street in the village of Clear Lake; milling off 2 inches of asphalt pavement and placing 3.25 inches of new asphalt; adding shoulder gravel to accommodate the highway profile increase; realigning the approach of County A/F at US 63 to achieve better sight distance at the intersection; realigning the approach of 60th Avenue at US 63; expanding the intersection tapers to meet current design standards; replacing guardrail; and cleaning, lining or repairing culverts and installing new end walls on some structures.
- Traffic impacts: Motorists will encounter lane closures controlled by flagging in work areas, and the US 63/County A intersection is closed.
Highway: WIS 65
- Location: North junction of Jewell Street in the St. Croix County village of Star Prairie to US 8 in the Polk County town of Balsam Lake
- Schedule: May 15 to September
- Cost: $8.85 million
- Description: Removing a portion of the existing asphalt pavement, overlaying the roadway with new asphalt pavement, creating a narrow, paved shoulder and reconstructing three areas of substandard vertical curves – one between the St. Croix/Polk County line and the curve just to the north and two stretches between 28th and 38th avenues in the Polk County town of Alden.
- Traffic impacts: WIS 65 is closed to through traffic, with a hard closure from 28th Avenue to 38th Avenue.
- Traffic is being detoured via WIS 64, WIS 46 and US 8.
Rusk County
Highway: County B
- Location: Main Creek Bridge south of Glen Flora
- Schedule: May 30 to September
- Cost: $737,856
- Description: Replacing the bridge.
- Traffic impacts: County B is closed at the bridge.
Sawyer County
- No current projects
Washburn County
Highway: WIS 77
- Location: County I west of the village of Minong east to County M
- Schedule: April 10 to late July
- Cost: $8.48 million
- Description: Removing a portion of the existing pavement and placing new asphalt pavement; cleaning, repairing or installing new culverts; reconstructing sidewalk curb ramps in the village of Minong; replacing deteriorated curb and gutter in the village of Minong; replacing guardrail; placing centerline rumble strips in rural areas; and installing new pavement markings.
- Traffic impacts: Motorists will encounter lane closures controlled by flagging in work zones in the rural segments.
Highway: US 53
- Location: Pine Grove Road southeast of Shell Lake to Wildcat Road southeast of Spooner
- Schedule: Aug. 15, 2022, to October 2023
- Cost: $16.8 million
- Description: Removing the existing pavement and a portion of the existing base course; placing a new base aggregate layer for drainage and new concrete pavement; replacing storm sewer, culverts, curb and gutter; reconstructing the approaches to US 53 from existing intersections; replacing shoulder rumble strips; and placing pavement markings.
- Traffic impacts: One lane of traffic in each direction is being maintained on the southbound lanes. Traffic is expected to be shifted to the new northbound lanes at either the end of the week or early the week after.
Last Update: Jul 07, 2023 5:23 pm CDT